June 3 dining Room report

Hello again:

It's only been a few days since I last posted some news about the Dining Romm at Lac L'Achigan. The progress is dramatic. Only last Friday there was all kinds of exterior wall not covered with the ''cement board'' cladding. It actually looks quite a bit like the old clapboard that was on the building. It is supposedly ''fire proof'' which was required due to the proximity of the Dining Room and the Staff Rec.
The flooring in the kitchen area is completely installed and the base baords are in, also. The hard wood floor in the Dining Room is just about all down. The construction worker was hard at work finishing it off during the site visit on June 3.
The electrician was actually installing the fixtures in the kitchen area. Everything had been pre-wired and now it is getting the fixtures in place.
The Dining Room is really bright and cheery! It is not quite the shade that had been chosen. the larger windows and the sky lights certainly let in a lot of light. It was a grey day and there was plenty of light.
Next week 3 coast of clear varnish will be applied to the floor in the main Dining Room. The kitchen equipment will start to be installed on Tuesday, June 8.
We are getting there. the staff arrive on June 19 for a week of training and 120 women arrive on June 25 for a 3 day weekend camp! Everything MUST be in order!
I will post more later.

I will try for a link.